Beyond The Time News

Sukkur Barrage Gates Replacement to Be Completed on Schedule

SUKKUR: According to Beyond Time News, Sindh Irrigation Minister Jam Khan Shoro has confirmed that the ongoing rehabilitation work at the Sukkur Barrage will be completed within the planned timeline.

During a visit to the site on Monday, the minister said the replacement of all gates is progressing smoothly. A Chinese company is carrying out the work, and all 44 gates are expected to be replaced by June 26 this year.


Multi-Billion Rupee Rehabilitation Project

The minister said the project will cost around Rs17 to 18 billion. He added that the next phase will include upgrades to the right and left pockets as well as the gates of canals linked to the barrage.

He also noted that further rehabilitation work on off-taking canals will continue next year.


Climate Change Concerns and Water Management

Jam Khan Shoro warned that climate change could increase the risk of drought in Sindh. He said the provincial government is providing support to farmers affected by shifting weather patterns.

He stressed that better water management is essential, especially as Sindh contributes very little to global emissions but faces severe climate impacts.

The minister also highlighted ongoing efforts to remove silt from canals, saying it remains a long-standing issue affecting water flow.

Read more:Iran FM says talks with US ‘scheduled’ for Friday in Oman


Project to Extend Barrage Life by 30 Years

Under the Sindh Barrages Improvement Project, major upgrades are underway, including:

  • Replacement of barrage gates
  • Dredging of the river upstream
  • Construction of a coffer dam

Officials say these improvements will extend the life of Sukkur Barrage by around 30 years.

The minister further stated that nearly 80% of Sindh’s agriculture depends on water from this barrage, making its rehabilitation critical for food security and farming stability.


Long-Term Water Security Focus

Authorities also plan to replace gates of multiple off-taking canals after the main barrage work is completed. The project is aimed at improving water distribution, reducing losses, and strengthening irrigation infrastructure across Sindh.